Dordabis Project Overview

The Dordabis project will be an open pit mining operation using a conventional gravity and magnetic separation processing route to produce 2.0 MTPY of high grade iron ore concentrates (68% Fe) with an expected life of mine of over 17 years.


Location

The Dordabis project is located 20km north of the town of Dordabis and 75km south east of the capital city of Namibia, Windhoek. The mine site is 522km via rail from the deep water port of Walvis Bay.

Licensing
and Tenure

The mining license and three contiguous exclusive prospecting licenses (EPL’s) were granted by the Government of the Republic of Namibia in 2014 and are all active.

A complete Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP) have also been completed by Lodestone and approved by Namibia’s Ministry of Environment and Tourism.

Current Activities

Local Consumers
of Lump Ore


Cheetah Cement


Ohorongo Cement


Niche Product
Pilot Plant


A demonstration plant which will produce 10ktpa of 71% Fe magnetite concentrate is planned to be in operation by Q1 2020.

Study Updates